BRUCE SGH-3015 Great Bridge Project

    The job is for bridge piling of 2.5 m steel pipe pile and 45 m long driving by
    HPSI 2000 Vibro for initial driving and final driving is by BRUCE SHG-3015,
    30 ton Ram weight and 1.5 m maximum stroke.
    Due to less driving power from the HPSI 2000 Vibro, it is driving by Impact
    Hammer and we have supplied suitable housing and drive cap to suit 2.5
    meter diameter steel pipe pile.
    And further more for saving the cost of power pack, we supplied our
    econonic modified manifold block to HPSI's 1200 power pack and it was
    simple to us combo Style used Vibro and Hammer of BRUCE SGH-3015.
    The required Hammer horse power is around 650 HP and it can be suitable
    any power pack higher 650 HP size and can be modified simply and we can
    supply only Hammer to customer.

    The project of above bridge is that name of Incheon Great Bridge and total
    length of bridge is 12 km long and total pile numbers of driving is around
    400 piles.